Delhi CM Rekha takes stock of metro and flyover projects; says will help ease congestion

Delhi CM Rekha takes stock of metro and flyover projects; says will help ease congestion

  • Updated On Apr 13, 2026 at 08:26 AM IST
Delhi CM Rekha Gupta

Several key Delhi Metro corridors and major flyover projects are set for completion by December, with work gathering pace across priority stretches, chief minister Rekha Gupta said on Sunday after reviewing ongoing work.

Chairing a high-level meeting at the Delhi secretariat, Gupta said corridors such as Krishna Park extension to Deepali Chowk (around 6.6 km), Majlis Park to Derawal Nagar (3.5 km), Derawal Nagar to R.K. Ashram (7.4 km), Tughlakabad to Sangam Vihar (6.3 km), Sangam Vihar to Saket G Block (4.3 km) and Saket G Block to Aerocity (12.6 km) are targeted for completion by the end of this year.

Officials said the Phase IV expansion of the network has progressed 80 per cent. At present, Delhi Metro spans 416 km, covering 303 stations across 12 lines with 32 interchange stations. An additional 104.45 km with 81 stations is under construction.

The chief minister said that some stretches under Phase IV such as Majlis Park to Maujpur, Deepali Chowk to Majlis Park and Janakpuri West to Krishna Park Extension are already operating.

Alongside the Metro expansion, flyover projects nearing completion would also ease congestion. A 2.16-km double-decker flyover from Azadpur to Tripolia Chowk, designed to carry both metro and road traffic, is about 73 per cent complete, while a 1.40-km flyover from Yamuna Vihar to Bhajanpura has reached around 85 per cent completion.In south Delhi, work is under way on a 2.48-km six-lane flyover from Saket G Block to Sangam Vihar along MB Road, along with underpasses at Saket G Block and Ambedkar Nagar.The project has achieved around 40 per cent progress so far. Design and alignment work is also in progress for a 2.53-km flyover from Maa Anandmayee Marg to Pul Prahladpur, with issues such as ASI permissions, tree cutting and land acquisition being addressed.

Officials said that work has begun on the remaining three Phase IV corridors – Lajpat Nagar to Saket G Block, Inderlok to Indraprastha and Rithala to Kundli – with a completion timeline of March 2029. Phase V(A) projects, including RK Ashram Marg to Indraprastha, Aerocity to IGI Airport Terminal 1 and Tughlakabad to Kalindi Kunj, have also been initiated.

  • Published On Apr 13, 2026 at 08:25 AM IST

Join the community of 2M+ industry professionals.

Subscribe to Newsletter to get latest insights & analysis in your inbox.

All about ETAuto industry right on your smartphone!

Related posts

MCG partners for 25 battery swapping stations to boost EV adoption and reduce air pollution

Delhi

Haryana hikes minimum wages 35% after unrest linked to Iran war cost pressures: Report

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Read More